Within three days in late August, local officials in two states answered the same question three different ways. The question was what a local government can do when someone wants to build a data center, or something close to one, on land it has never had to think hard about.
On August 25, the Floyd County Commission in Georgia adopted an ordinance. The same day, the Association of County Commissions of Alabama passed a resolution saying, in effect, that most of its members cannot do much at all. Two days later, the City of Anniston imposed a 12-month moratorium. And in Bradley County, Tennessee, residents have spent two weeks at meetings and protests over a proposal whose land-use decision will be made by a city council.
My argument is simple, and it is the same one I would make about sign ordinances or hotel height limits. The time for a county to write its rules is before anyone has asked for anything. Floyd County did that. The others are finding out what it costs not to.
Start with what Floyd County actually passed, because the details are the point. Data centers are limited to the Heavy Industrial district. Developers must file a decommissioning plan covering equipment removal, hazardous materials, soil and groundwater testing, and site restoration, and must back it with a bond, escrow account, or letter of credit sized to the full cost. Closed-loop cooling is prioritized, and private wells and direct connections to surface water are prohibited. Noise is capped at 65 decibels by day and 55 by night at residential property lines. Buildings must sit 600 feet from existing homes. Violations can cost $1,000 a day, which the Rome-Floyd County planning director, Brice Wood, noted is the most state law allows.
It reads like a price list. A developer reading it knows, before spending a dollar on engineering, what the county will require. A resident reading it knows what the county has promised. Both sides can argue about whether 600 feet is enough, but they are arguing about a number, in public, before a site is chosen.
The decommissioning bond is the line I would copy first. These facilities are built around technology that changes quickly, and nobody can promise a county what a large building full of servers will be worth in 20 years. A county that requires the cost of removal to be set aside up front has answered that question in advance. A county that does not has left it to whoever is in office when the building goes quiet.
Alabama shows the other end. According to the Alabama Political Reporter, the association’s executive director, Sonny Brasfield, said most county commissions lack adequate authority to impose moratoriums in unincorporated areas. The association’s resolution opposes zoning powers written for a single industry, pointing to the earlier fight over solar farms, and asks the Legislature instead to recognize county planning and zoning authority more broadly. I think the association has this right. A power granted industry by industry arrives after the fight it was needed for.
Which brings me to Bradley County. Project River would put an $11.3 billion campus on about 850 acres along the Hiwassee River, powered by a 500-megawatt plant burning Southern pine and two natural gas plants. Its chief executive, Mitchell Simpson, has said a data center is “very likely” but that the campus could power something else. The company claims up to 2,600 jobs. The property has been submitted for annexation into the City of Cleveland, along with a land-use change, so the decision will rest with a council elected by city voters.
I am not going to tell Bradley County whether to want Project River. That is a decision for the people who will live beside it, and the reporting so far suggests many of them do not. My point is narrower. The residents at those meetings are arguing about truck counts, noise, and water after the site was chosen, on a timeline set by the applicant, before a city council that residents outside the city do not elect. That is the weakest position a community can argue from. It is what happens, through no fault of theirs, when the rules get written in response to a proposal instead of ahead of one.
There is a boosterish reading of all this in which any rule is a signal that a county is closed for business. Floyd County is the evidence against it. Its commission told the next applicant what the terms are and left the door open.
The counties along the Cumberland Plateau and down the Tennessee River have more cheap land, more water, and more quiet than almost anywhere a developer is looking right now. They should assume the question is coming. Ask your county commission what it would require of a data center today, and in what document. If the answer is that it has never come up, that is the answer to act on.